Post-registration change requests for prior approval – finalized

Prior approval requests pending publication | Published prior approval requests pending finalization | Search finalized prior approval and issuance track requests


Reference of post-registration change request PRC-
Project reference PA-
Process track Any
Prior approval
Issuance
Type of request Find requests with ANY ALL of the types:

Changes to the project design as described in the registered generic CPA-DD (CGCPA)
Temporary deviations from the monitoring plan or the monitoring methodology (TDEV)
Corrections that do not affect project design (CORR)
Permanent changes from the monitoring plan or the monitoring methodology (CGMPMETH)
Changes specific to A/R project activities (CGAR)
Inclusion of a monitoring plan in the registered PDD, PoA-DD or CPA-DD (INCLMP)
Addition of specific case CPA DDs corresponding to generic CPA DDs (ADDCPA)
Changes to the project or programme design (CGPD)
Change to the start date of the crediting period (CGCP)

Final status

There are 1663 matching requests:

Displaying 41-60 of 1663

Reference Title Current state Last update
PRC-10368-002 Grid-connected Solar PV project in Mérina Dakhar Approved
2019/07/03 17:41:10.473929 GMT+2
03 Jul 19
PRC-10361-001 Renewable Energy Project by Pramatha Power Pvt. Ltd. Goa (EKIESL- CDM. April 16-04) Approved
2023/09/20 19:18:59.400755 GMT+2
20 Sep 23
PRC-10345-001 Institutional Improved Cook Stoves for Schools and Institutions in Uganda Approved
2019/11/20 09:34:23.484671 GMT+1
20 Nov 19
PRC-10344-001 Bundled Wind Power Project by EKI Energy Services Limited (EKIESL-CDM.April-13-02) Approved
2024/01/04 09:08:0.993303 GMT+1
04 Jan 24
PRC-10341-004 MicroEnergy Credits – Microfinance for Clean Energy Product Lines – Africa Approved
2021/05/11 08:32:52.214736 GMT+2
11 May 21
PRC-10341-003 MicroEnergy Credits – Microfinance for Clean Energy Product Lines – Africa Approved
2020/11/05 08:44:36.459612 GMT+1
05 Nov 20
PRC-10341-001 MicroEnergy Credits – Microfinance for Clean Energy Product Lines – Africa Approved
2019/11/11 18:24:33.898716 GMT+1
11 Nov 19
PRC-10335-001 New gas fired power plant at Ressano Garcia Approved
2022/09/12 09:03:16.538270 GMT+2
12 Sep 22
PRC-10331-001 Grid-connected Solar PV project in Bokhol Approved
2020/09/08 10:40:25.390704 GMT+2
08 Sep 20
PRC-10330-002 Fauji Cement Company Limited Waste Heat Recovery Project Approved
2023/02/09 09:24:22.267301 GMT+1
09 Feb 23
PRC-10327-002 Grid-connected Solar PV project in Méouane Approved
2019/11/11 09:32:12.062213 GMT+1
11 Nov 19
PRC-10327-001 Grid-connected Solar PV project in Méouane Approved
2019/06/24 11:15:32.415107 GMT+2
24 Jun 19
PRC-10320-001 Scaling-Up Solar Photovoltaic Power Generation Approved
2018/05/09 15:21:52.442881 GMT+2
09 May 18
PRC-10304-001 Energia dos Ventos I, II, III, IV and X CDM Project (JUN1184), Brazil Approved
2019/08/05 11:58:15.136765 GMT+2
05 Aug 19
PRC-10291-001 NURU Light - Cameroon Approved
2018/01/25 10:29:34.147723 GMT+1
25 Jan 18
PRC-10288-001 Solar Power Project by Fortum FinnSurya (EKIESL-CDM.February-15-01) Approved
2021/02/18 09:39:42.279767 GMT+1
18 Feb 21
PRC-10286-002 Brazilian PoA for NAMA incentivized NCRE Projects Approved
2024/02/20 08:34:40.870680 GMT+1
20 Feb 24
PRC-10286-001 Brazilian PoA for NAMA incentivized NCRE Projects Approved
2024/02/26 09:00:40.805404 GMT+1
26 Feb 24
PRC-10285-002 Ethiopia Off-Grid Renewable Energy Program Approved
2019/02/04 16:28:19.206303 GMT+1
04 Feb 19
PRC-10285-001 Ethiopia Off-Grid Renewable Energy Program Approved
2018/10/02 18:06:0.352108 GMT+2