Project: 10327 Grid-connected Solar PV project in Méouane - Request for post-registration changes
Project 10327 Grid-connected Solar PV project in Méouane
PRC ref PRC-10327-001
Process track Prior approval
DOE Carbon Check
Methodology(ies) and/or Standardized Baseline(s)
applied at the post-registration changes
Methodology(ies) list
Standardized baseline(s) list
DOE conducted validation of the changes Prior to commencement of a verification for the project activity or PoA stated above
Type of submission Corrections that do not affect project design
  • All changes are in Appendix 1 of the CDM project standard?

Permanent changes from the monitoring plan or the monitoring methodology
  • All changes are in Appendix 1 of the CDM project standard? No
Applicable crediting period 28 Jul 17 - 27 Jul 24
Assessment opinion Assessment opinion (739 KB)
Revised PDD Revised PDD (1545 KB)   Revised PDD - track changes (1547 KB)
Supplementary documents
Signed form Signed form (2166 KB)
DOE clarification
VVS version VVS-PA 2.0
Current status 24 Jun 19 - Approved
Effective approval date: 23 Jun 19
Historic statuses 20 May 19 - Published
20 May 19 - Summary note being prepared
03 Jun 19 - Awaiting EB decision