21:28 25 Oct 25
Project:
10361 Renewable Energy Project by Pramatha Power Pvt. Ltd. Goa (EKIESL- CDM. April 16-04)
- Request for post-registration changes
| Project | 10361 Renewable Energy Project by Pramatha Power Pvt. Ltd. Goa (EKIESL- CDM. April 16-04) |
|---|---|
| PRC ref | PRC-10361-001 |
| Process track | Prior approval |
| DOE | LGAI Tech. Center S.A |
|
Methodology(ies) and/or Standardized Baseline(s)
applied at the post-registration changes |
No changes |
| Methodology(ies) list | |
| Standardized baseline(s) list | |
| DOE conducted validation of the changes | Prior to commencement of a verification for the project activity or PoA stated above |
| Type of submission |
Corrections that do not affect project design
Permanent changes from the monitoring plan or the monitoring methodology
|
| Applicable crediting period | 15 May 17 - 14 May 24 |
| Assessment opinion |
Assessment opinion (224 KB)
|
| Revised PDD |
Revised PDD (751 KB)
Revised PDD - track changes (778 KB)
|
| Supplementary documents |
Appendix 1 - ER UN 10361 TQC 9422 TC.xlsx (30 KB)
|
| Signed form |
Signed form (158 KB)
|
| DOE clarification | |
| VVS version | VVS-PA 3.0 |
| Current status | 20 Sep 23 -
Approved
Effective approval date: 03 Sep 23
|
| Historic statuses |
31 Jul 23 -
Published 31 Jul 23 - Summary note being prepared 14 Aug 23 - Awaiting EB decision |

Assessment opinion
Appendix 1 - ER UN 10361 TQC 9422 TC.xlsx
Offset now: visit the United Nations Carbon Offset Platform