12:43 18 May 25
Project:
2761 Conversion of existing open cycle gas turbine to combined cycle at Guaracachi power station, Santa Cruz, Bolivia
- Issuance Request
Project | 2761: Conversion of existing open cycle gas turbine to combined cycle at Guaracachi power station, Santa Cruz, Bolivia |
---|---|
ISSUANCE STATUS | Issued (on 25 Jan 19) completeness check | info & rep check: concluded |
Monitoring period | 01 Jan 15 - 31 Dec 16 |
Monitoring report |
![]() |
Request for issuance |
![]() |
Amount of CERs |
CERs issued from 01 Jan 2013 until 31 December 2020:
356,766
Serial Range:
Block start: BO-5-2516510-2-2-0-2761
Block end: BO-5-2873275-2-2-0-2761
|
Verification and certification reports |
VVS/VVM version:
VVS-PA 1.0
![]() ![]() |
Additional documents |
![]() ![]() 2761 3 EF Calculation (1280 KB) ![]() |
Previous submissions
Submission date | Outcome |
---|---|
22 Jun 18 | CC complete | I&R incomplete |
Offset now: visit the United Nations Carbon Offset Platform