23:02 17 May 25
Project:
2761 Conversion of existing open cycle gas turbine to combined cycle at Guaracachi power station, Santa Cruz, Bolivia
- Crediting Period Renewal Request
[]
Project |
2761: Conversion of existing open cycle gas turbine to combined cycle at Guaracachi power station, Santa Cruz, Bolivia
- ![]() PDD appendices ![]() - ![]() |
---|---|
Methodologies Used |
ACM0007 ver. 6 -
Conversion from single cycle to combined cycle power generation
|
VVS Version | VVS 9.0 |
Standardized baselines used | N/A |
Amount of Reductions | 165,708 metric tonnes CO2 equivalent per annum |
Validation Opinion |
![]() |
Renewal Date |
03 Oct 17
(Renewable - Expired)
(view history)
completeness check: complete
info & rep check: concluded
Renewal no longer possible
|
Crediting Period (requested for renewal) |
13 Apr 17 - 12 Apr 24
Other crediting period(s): 13 Apr 10 - 12 Apr 17 |
Requests for Issuance
and related documentation |
|
Offset now: visit the United Nations Carbon Offset Platform
Connect with us: