Project:
7727 Grid connected combined cycle power plant project in Qadirpur utilizing permeate gas, previously flared
- Issuance Request
Project | 7727: Grid connected combined cycle power plant project in Qadirpur utilizing permeate gas, previously flared |
---|---|
ISSUANCE STATUS | Issued (on 04 Oct 22) completeness check: complete | info & rep check: concluded |
Monitoring period | 01 Jan 13 - 31 Dec 19 |
Monitoring report | Monitoring report (833 KB) |
Submission of comments to the DOE | |
Requests for post-registration changes containing applicable deviations | PRC-7727-001 - Approved |
Requests for post-registration changes submitted with the issuance request | PRC-7727-001 |
Request for issuance | Signed form (239 KB) |
Amount of CERs |
CERs issued from 01 Jan 2013 until 31 December 2020:
3,327,146
Serial Range:
Block start: PK-5-11930400-2-2-0-7727
Block end: PK-5-15257545-2-2-0-7727
|
Verification and certification reports |
VVS/VVM version:
VVS-PA 3.0
Certification report (1254 KB) Verification report (1254 KB) |
Additional documents |
10 August 2022_MR1_CCPP_Qadirpur (1297 KB)
10 August 2022_ER_CCPP_Qadirpur (738 KB) EF 2013-2019 (443 KB) |
Previous submissions
Submission date | Outcome |
---|---|
03 Jul 22 | CC incomplete | I&R |