18:06 18 May 25
Project:
0599 Jilin Taonan Wind Power Project
- Issuance Request
Project | 0599: Jilin Taonan Wind Power Project |
---|---|
ISSUANCE STATUS | Issued (on 20 Mar 08) |
Monitoring period | 01 Dec 06 - 24 Nov 07 |
Monitoring report |
![]() |
Request for issuance |
![]() Before corrections: ![]() |
Amount of CERs |
CERs issued up to 31 December 2012:
93,539
Serial Range:
Block start: CN-5-37332535-1-1-0-599
Block end: CN-5-37426073-1-1-0-599
Before corrections: 93539 |
Verification and certification reports |
![]() ![]() Before corrections: ![]() ![]() |
Additional documents |
![]() ![]() Before corrections: ![]() ![]() |
Request for review |
Request 1