Project: 0346 Nueva Aldea Biomass Power Plant Phase 2 - Issuance Request
Project 0346: Nueva Aldea Biomass Power Plant Phase 2
 
ISSUANCE STATUS Issued (on 22 Mar 18)   completeness check | info & rep check: concluded
Monitoring period 01 Apr 14 - 31 Dec 15
Monitoring report Monitoring report (786 KB)
Requests for post-registration changes containing applicable deviations PRC-0346-003 - Approved
Requests for post-registration changes submitted with the issuance request PRC-0346-003
 
Request for issuance Signed form (2218 KB)
Amount of CERs CERs issued from 01 Jan 2013 until 31 December 2020: 88,840
Serial Range: Block start: CL-5-28529748-2-2-0-346     Block end: CL-5-28618587-2-2-0-346
Verification and certification reports VVS/VVM version: VVS 9.0
Certification report (2126 KB)
Verification report (2126 KB)
Additional documents Monitoring report (1029 KB)
0346 1 CER Calculation (66 KB)
0346 1 Response to Incompleteness Notification (327 KB)
0346 MP2 1 Balance 2014 (480 KB)
0346 MP2 1 Balance 2015 (509 KB)

Previous submissions

Submission date Outcome
25 Jul 17 CC complete | I&R incomplete
01 Dec 17 CC complete | I&R