13:12 27 Dec 24
Project:
0346 Nueva Aldea Biomass Power Plant Phase 2
- Issuance Request
Project | 0346: Nueva Aldea Biomass Power Plant Phase 2 |
---|---|
ISSUANCE STATUS | Issued (on 22 Mar 18) completeness check | info & rep check: concluded |
Monitoring period | 01 Apr 14 - 31 Dec 15 |
Monitoring report | Monitoring report (786 KB) |
Requests for post-registration changes containing applicable deviations | PRC-0346-003 - Approved |
Requests for post-registration changes submitted with the issuance request | PRC-0346-003 |
Request for issuance | Signed form (2218 KB) |
Amount of CERs |
CERs issued from 01 Jan 2013 until 31 December 2020:
88,840
Serial Range:
Block start: CL-5-28529748-2-2-0-346
Block end: CL-5-28618587-2-2-0-346
|
Verification and certification reports |
VVS/VVM version:
VVS 9.0
Certification report (2126 KB) Verification report (2126 KB) |
Additional documents |
Monitoring report (1029 KB)
0346 1 CER Calculation (66 KB) 0346 1 Response to Incompleteness Notification (327 KB) 0346 MP2 1 Balance 2014 (480 KB) 0346 MP2 1 Balance 2015 (509 KB) |
Previous submissions
Submission date | Outcome |
---|---|
25 Jul 17 | CC complete | I&R incomplete |
01 Dec 17 | CC complete | I&R |
Offset now: visit the United Nations Carbon Offset Platform