13:30 03 Apr 25
Project:
0298 4.5 MW Biomass (low density Crop Residues) based Power Generation unit of Malavalli Power Plant Pvt Ltd.
- Issuance Request
Project | 0298: 4.5 MW Biomass (low density Crop Residues) based Power Generation unit of Malavalli Power Plant Pvt Ltd. |
---|---|
ISSUANCE STATUS | Issued (on 20 Feb 07) |
Monitoring period | 01 Aug 01 - 30 Jun 06 |
Monitoring report |
![]() |
Request for issuance |
![]() |
Amount of CERs |
CERs issued up to 31 December 2012:
77,294
Serial Range:
Block start: IN-5-15300750-1-1-0-298
Block end: IN-5-15378043-1-1-0-298
|
Verification and certification reports |
![]() ![]() |
Additional documents |
![]() ![]() ![]() |
Request for review |
Request 1
Request 2 Request 3 EB meeting: EB29 (at which the Board considers the request(s) for review, decides whether to undertake the review and, if so, determine its scope and selects a review team) Initial comments: ![]() ![]() |