Project: 0298 4.5 MW Biomass (low density Crop Residues) based Power Generation unit of Malavalli Power Plant Pvt Ltd. - Issuance Request
Project 0298: 4.5 MW Biomass (low density Crop Residues) based Power Generation unit of Malavalli Power Plant Pvt Ltd.
 
ISSUANCE STATUS Issued (on 20 Feb 07)  
Monitoring period 01 Aug 01 - 30 Jun 06
Monitoring report Monitoring report (124 KB)
 
Request for issuance Signed form (133 KB)
Amount of CERs CERs issued up to 31 December 2012: 77,294
Serial Range: Block start: IN-5-15300750-1-1-0-298     Block end: IN-5-15378043-1-1-0-298
Verification and certification reports Certification report (222 KB)
Verification report (222 KB)
Additional documents MONITORING DATA 1 (98 KB)
MONITORING DATA 2 (30 KB)
Revised monitoring report (v 02) (124 KB)
Request for review Request 1
Request 2
Request 3


EB meeting: EB29
(at which the Board considers the request(s) for review, decides whether to undertake the review and, if so, determine its scope and selects a review team)

Initial comments:
Initial comments by the DOE (171 KB)
Initial comments by the project participants (36 KB)