11:38 04 Dec 24
Project:
0259 Trupan Biomass Power Plant in Chile
- Issuance Request
Project | 0259: Trupan Biomass Power Plant in Chile |
---|---|
ISSUANCE STATUS | Issued (on 29 Apr 09) |
Monitoring period | 01 Oct 07 - 30 Sep 08 |
Monitoring report | Monitoring report (221 KB) |
Request for issuance |
Signed form (291 KB)
Before corrections: Signed form (915 KB) |
Amount of CERs |
CERs issued up to 31 December 2012:
154,309
Serial Range:
Block start: CL-5-3011478-1-1-0-259
Block end: CL-5-3165786-1-1-0-259
Before corrections: 158306 |
Verification and certification reports |
Certification report (259 KB)
Verification report (259 KB) Before corrections: Certification report (257 KB) Verification report (257 KB) |
Additional documents |
Revised CER Spreadsheet (254 KB)
Revised Emmission Factor SIC 2007-2008 (451 KB) Revised Monitoring report V3 MP3 (308 KB) Lambda SIC - Jan-Dec 2008 (2080 KB) Before corrections: Monitioring Report V2 Mp3 (308 KB) CER Spreadsheet (254 KB) |
Request for review |
Request 1
Request 2 Request 3 |