21:04 04 Dec 24
Issuance Request for Review Form
CDM project activity/programme of activities issuance request review form (CDM-ISSR-FORM) (Version 03.0) |
---|
Project title of the project activity or programme of activities (PoA) for which issuance is requested | Trupan Biomass Power Plant in Chile (0259) |
---|---|
DOE that requested for issuance and date of request | SGS (09 Mar 09) |
Please indicate, in accordance with paragraphs 65 of the CDM modalities and procedures, for which reason(s) you request review | |
Incompetence | |
Please indicate reasons for the request for review | |
OTHER ISSUES:
As the grid emission factor for 2008 was calculated only based on 9-month data, corrections are required to be submitted by applying 2007 grid emission factor in line with ACM0002 in the calculation of emission reduction for this whole monitoring period. The DOE is required to submit a new request for issuance form which corresponds to the corrected certified emission reductions. |
|
Date | 03 Apr 09 |