11:39 09 Nov 25
Project
10403 :
70 MW Bhadla Solar power plant by Fortum Finnsurya Energy Pvt Ltd (EKIESL-CDM-APRIL-16-01)
| Project title |
70 MW Bhadla Solar power plant by Fortum Finnsurya Energy Pvt Ltd (EKIESL-CDM-APRIL-16-01)
- project design document (701 KB)
(approved -
-
23 Dec 2019 -
view previous)
PDD appendices Appendix 1 - 2017_1316_IRR (81 KB)
Appendix 2 - 2017_1316_ER (2566 KB)
- registration request form (142 KB)
|
|---|---|
| SDC description report | Not Available. Please refer to our Further Information on SD-Tool |
| Host Parties |
India
, involved indirectly
approval (1123 KB)
authorization (1123 KB)
Authorized Participants: Fortum FinnSurya Energy Private Limited |
| Other Parties Involved |
Australia
, involved indirectly
approval (264 KB)
authorization (264 KB)
Authorized Participants: EKI Energy Services Limited Germany , involved indirectly approval (1013 KB)
authorization (1013 KB)
Authorized Participants: First Climate Markets AG |
| Sectoral scopes | 1 : Energy industries (renewable - / non-renewable sources) |
| Activity Scale | LARGE |
| Methodologies Used |
ACM0002 ver. 17 -
Grid-connected electricity generation from renewable sources
|
| Standardized baselines used | N/A |
| Amount of Reductions | 119,384 metric tonnes CO2 equivalent per annum |
| Fee level | USD 22376.8 |
| Validation Report |
VVS/VVM version:
VVS 9.0
Validation report (492 KB)
Public availability information
Link to information uploaded for public availability Validation opinion on changes in PDD (285 KB)
|
| Modalities of Communication |
MoC Annex 1 Modalities of Communication valid as of 09/07/2018 MoC Annex 2 (Add Project Participant) valid as of 15/07/2022 MoC Annex 2 (Change/update authorized signatory, name or contact details) valid as of 23/06/2021 MoC Annex 2 (Add Project Participant) valid as of 25/06/2020 |
| Registration Date | 06 Nov 17 (view history) completeness check: complete info & rep check: concluded |
| Crediting Period | 06 Nov 17 - 05 Nov 24 (Renewable) |
| Requests for Issuance
and related documentation |
Monitoring report: 06 Nov 2017 - 01 Apr 2019 (811 KB)Issuance request state: Issued CERs requested from 01 Jan 2013 until 31 December 2020: 201309 Serial Range: Block start: IN-5-255855651-2-2-0-10403 Block end: IN-5-256056959-2-2-0-10403 [Full view and history] Monitoring report: 02 Apr 2019 - 01 Aug 2020 (767 KB)Issuance request state: Issued CERs requested from 01 Jan 2013 until 31 December 2020: 194964 Serial Range: Block start: IN-5-264571446-2-2-0-10403 Block end: IN-5-264766409-2-2-0-10403 [Full view and history] Monitoring report: 02 Aug 2020 - 31 Dec 2020 (436 KB)Issuance request state: Issued CERs requested from 01 Jan 2013 until 31 December 2020: 57739 Serial Range: Block start: IN-5-290849553-2-2-0-10403 Block end: IN-5-290907291-2-2-0-10403 [Full view and history] |

project design document
Appendix 1 - 2017_1316_IRR
Offset now: visit the United Nations Carbon Offset Platform
Connect with us: