Project: 10403 70 MW Bhadla Solar power plant by Fortum Finnsurya Energy Pvt Ltd (EKIESL-CDM-APRIL-16-01) - Issuance Request
Project 10403: 70 MW Bhadla Solar power plant by Fortum Finnsurya Energy Pvt Ltd (EKIESL-CDM-APRIL-16-01)
 
ISSUANCE STATUS Issued (on 25 Mar 21)   completeness check: complete | info & rep check: concluded
Monitoring period 02 Apr 19 - 01 Aug 20
Monitoring report Monitoring report (767 KB)
 
Request for issuance Signed form (363 KB)
Amount of CERs CERs issued from 01 Jan 2013 until 31 December 2020: 194,964
Serial Range: Block start: IN-5-264571446-2-2-0-10403     Block end: IN-5-264766409-2-2-0-10403
Verification and certification reports VVS/VVM version: VVS-PA 2.0
Certification report (448 KB)
Verification report (448 KB)
Additional documents Final MR (740 KB)
ER calculation sheet (28 KB)