21:14 17 Nov 24
Project:
10403 70 MW Bhadla Solar power plant by Fortum Finnsurya Energy Pvt Ltd (EKIESL-CDM-APRIL-16-01)
- Request for post-registration changes
Project | 10403 70 MW Bhadla Solar power plant by Fortum Finnsurya Energy Pvt Ltd (EKIESL-CDM-APRIL-16-01) |
---|---|
PRC ref | PRC-10403-001 |
Process track | Issuance |
DOE | Earthood |
Methodology(ies) and/or Standardized Baseline(s)
applied at the post-registration changes |
No changes |
Methodology(ies) list | |
Standardized baseline(s) list | |
DOE conducted validation of the changes | When performing a verification for the project activity or PoA stated above (See footnote 1 below) |
Type of submission |
Corrections that do not affect project design
|
Applicable crediting period | 06 Nov 17 - 05 Nov 24 |
Assessment opinion | Assessment opinion (285 KB) |
Revised PDD | Revised PDD (701 KB) Revised PDD - track changes (832 KB) |
Supplementary documents | |
Signed form | Signed form (247 KB) |
DOE clarification | |
VVS version | VVS-PA 2.0 |
Current status | 23 Dec 19 -
Approved
Effective approval date: 23 Dec 19
|
Historic statuses |
22 Nov 19 -
Request published |
Offset now: visit the United Nations Carbon Offset Platform
Connect with us: