M-DEV0390: Contractual requirement to enable a fuel switch to a primary fuel other than natural gas during the gas supply interruption situation or emergency situation

Reference M-DEV0390
Submitted by TÜV NORD (11 Dec 2010)
Project activity Ranhill Powertron II 190 MW Gas Fired CCPP Project
Concerned methodology(ies)
AM0029 ver. 3: Baseline Methodology for Grid Connected Electricity Generation Plants using Natural Gas
Title/subject of deviation Contractual requirement to enable a fuel switch to a primary fuel other than natural gas during the gas supply interruption situation or emergency situation
PDD PDD (894 KB)
Description
The applicability criterion, which is referred to by this request for deviation, is as follows:

The project activity is the construction and operation of a new natural gas fired grid-connected
electricity generation plant;1
with
1 Natural gas should be the primary fuel. Small amounts of other start-up or auxiliary fuels can be used, but can comprise no more than 1% of total fuel use, on energy basis.

This footnote is the reason for this request for deviation when discussing the compliance of the project activity, which is the construction and operation of a new natural gas fired grid-connected electricity generation plant. But, as this plant plays a major role in the expansion plan of the relatively small grid of Sabah (East Malaysia, Borneo), and will receive high ranking in the dispatch order and is therefore considered as a base-load plant, the operator’s contract includes the obligation to set-up the plant in a manner that allows the immediate switch to another fuel independent from the gas pipeline (single-line-system) even in case of long-term interruptions. Thus it has been decided to install as secondary fuel supply system based on distillate fuel oil, which will be used during maintenance periods or emergency situations of the supplying pipeline. There is a tank farm for distillate fuel oil installed at the project operation which enables the continuous operation for seven days.
When the plant is fuelled by natural gas, the compliance with the 1% threshold for start-up and auxiliary usage can be ensured by existing evidences (design and records from similar plants), but in theory the primary fuel ight be different from natural gas for limited periods under the regular maintenance scheme of the gas supply system or even undefined periods in the case of emergencies. The duration of such periods is not under control of the project participants, as it would only become relevant when there is an interruption of the gas supply by the gas supplier or emergency situation. Due to the purchase and delivery contract the gas supplier has to provide documented information in case he intends or is urged to interrupt the gas supply. According to the special arrangements as used for such independent power utilities, the operator would have financially neither losses nor benefits, when switching the fuel type. In conclusion a registration as CDM project would even form a strong incentive for remaining at natural gas as preferred fuel.
The experience from the adjacent Ranhill 1 power plant is that by regular maintenance, the distillate fuel oil consumption will be much less than 1% of the gas consumption on energy basis, on the other hand this threshold is applicable for parallel usage and not for alternative usage. By applying the given formulae for the auxiliary or start-up usage of other fossil fuel, the project emissions can be calculated also for the period of alternative usage. This approach is suggested by the underlying PDD, but it deviates from the methodology as it does not only address auxiliary but alternate liquid fossil fuel, too. There is no risk that this situation would lead to an overestimation of emission reduction. Even more, the CDM registration would form a further incentive to minimize such periods as far as possible (by pushing the contracted gas supplier).

TÜV Nord therefore recommends accepting this request for deviation.
Assessment
The given constellation is considered rather unique and therefore a request for deviation is more applicable than a request for revision. The situation that such a base-load plant is supplied by a single-line pipeline connected to a single off-shore gas field is also considered as unusual. This constellation creates the need for alternative solutions during maintenance periods or emergencies of the pipeline system. Hence TÜV Nord does not consider it necessary revising the methodology.
Impact
As written above there will be no impact with regard of determining the emissions reductions as the use of distillate fuel oil as primary fuel for short periods could be dealt with in the same manner and by the same formulae as for the use of the purpose of start-up or auxiliary fuel. As the baseline plant is a coal fired plant also the use of distillate fuel oil will lead to some (but less) emissions reductions compared to this baseline, which is outside the original intention of AM0029, which itself is considered being applicable for switching from more carbon intensive fuels to natural gas.

Hence TÜV Nord recommends giving advice in a manner that allows distillate fuel oil as primary fuel for limited periods only, when it can be clearly demonstrated that there was either a maintenance work done at the pipeline system or an emergency situation resulting in its disconnection.
Annexes Ranhill F-CDM-DEV-METH (71 KB)
Link to the documentation made available at validation stage Link to relevant documentation
Signed form Signed form (1757 KB)
Decision This request for deviation has not been accepted.

The Chair has decided not to accept the proposed request for deviation as the methodology does not address the following key issues and it will be required to substantially revise the methodology before project activity can be considered eligible under this methodology :

(a) the main intention of this methodology is to promote use of less carbon intensive NG as a fuel for electricity generation, therefore use of other auxiliary or start-up or alternate or secondary fuels beyond more than 1% is not allowed by the methodology. No information is provided on the source, energy content and costs of distillate fuel oil and whether distillate fuel oil is more or less carbon intensive and economical fuel than natural gas.
(b) the methodology does not mention the applicability condition regarding the diversion of distillate fuel oil to this project as it is not designed for the use of any other fuel than NG;
(c) the baseline alternatives/scenarios for the power generation from the combination of fuels (NG and distillate fuel oil) have not been defined, for which the existing methodology does not have any provision nor the has the PDD substantiated the appropriateness of the most economically attractive baseline and therefore baseline emissions and the additionality of the project activity;
(d) the methodology does not contain algorithms and formulae to calculate the project emissions from the combustion of alternate fuel (distillate fuel oil) and use of additional energy for transportation/ pumping of the alternate fuel (a liquid) as the methodology was only designed for calculating project emissions from only natural gas;
(e) the upstream emissions of using distillate fuel oil are not clear and the methodology does not contain algorithms and formulae to calculate the leakage emissions from the use of alternate fuel (distillate fuel oil) as the methodology was only designed for calculating leakage emissions from only natural gas;
(f) the methodology was not designed for this and does not mention to measure quantity of: (i) all types of fuel used, including the distillate fuel oil and (ii) electricity generated from distillate fuel oil; and
(g) it is not clear why the project cannot use LNG, considering that it is sufficiently available, almost equally carbon intensive fuel as NG and allowed by the methodology, instead of distillate fuel oil.

Current status 10 Feb 2011 - Deviation not accepted
Historic statuses 11 Dec 2010 - Submission received
08 Jan 2011 - Successfully passed the Completeness Check
26 Jan 2011 - Awaiting EB decision