03:13 09 Jul 25
Project
4590 :
Sichuan Kangding Sandaoqiao Hydropower Station
Project title |
Sichuan Kangding Sandaoqiao Hydropower Station
- ![]() - ![]() |
---|---|
SDC description report | Not Available. Please refer to our Further Information on SD-Tool |
Host Parties |
China
, involved indirectly
![]() ![]() Authorized Participants: Kangding Jineng Hydropower Exploitation Co., Ltd. |
Other Parties Involved |
Switzerland
, involved indirectly
![]() ![]() Authorized Participants: South Pole Carbon Asset Management Ltd. Austria , involved indirectly ![]() ![]() Authorized Participants: Kommunalkredit Public Consulting GmbH |
Sectoral scopes | 1 : Energy industries (renewable - / non-renewable sources) |
Activity Scale | LARGE |
Methodologies Used |
ACM0002 ver. 12 -
Consolidated baseline methodology for grid-connected electricity generation from renewable sources
|
Standardized baselines used | N/A |
Amount of Reductions | 107,054 metric tonnes CO2 equivalent per annum |
Fee level | USD 19910.8 |
Validation Report |
![]() Link to information uploaded for public availability ![]() |
Modalities of Communication |
MoC Annex 1 Modalities of Communication valid as of 18/11/2011 |
Registration Date | 19 Aug 11 (Date of registration action 16 Nov 11) (view history) completeness check: complete info & rep check: concluded |
Crediting Period |
19 Aug 11 - 18 Aug 18
(Renewable)
Subsequent crediting period(s): 19 Aug 18 - 18 Aug 25 |
Requests for Issuance
and related documentation |
Monitoring report: ![]() Issuance request state: Issued CERs requested up to 31 December 2012: 65406 Serial Range: Block start: CN-5-791138435-1-1-0-4590 Block end: CN-5-791203840-1-1-0-4590 [Full view and history] Monitoring report: ![]() Issuance request state: Issued CERs requested up to 31 December 2012: 93145 Serial Range: Block start: CN-5-861597302-1-1-0-4590 Block end: CN-5-861690446-1-1-0-4590 [Full view and history] |
Offset now: visit the United Nations Carbon Offset Platform
Connect with us: