2017 Hubei Lichuan Longqiao Hydropower Station
- Issuance Request
Project | 2017: Hubei Lichuan Longqiao Hydropower Station |
---|---|
ISSUANCE STATUS | Issued (on 23 Nov 12) completeness check: complete | info & rep check: concluded |
Monitoring period | 28 Nov 11 - 27 May 12 |
Monitoring report | Monitoring report (114 KB) |
Request for issuance | Signed form (101 KB) |
Amount of CERs |
CERs issued up to 31 December 2012:
101,003
Serial Range:
Block start: CN-5-655198995-1-1-0-2017
Block end: CN-5-655299997-1-1-0-2017
|
Verification and certification reports |
VVS/VVM version:
VVS 2.0
Certification report (88 KB) Verification report (323 KB) |
Additional documents |
ER sheet (42 KB)
Monitoring report (107 KB) |