12:54 22 May 24
Project:
2017 Hubei Lichuan Longqiao Hydropower Station
- Issuance Request
Project | 2017: Hubei Lichuan Longqiao Hydropower Station |
---|---|
ISSUANCE STATUS | Issued (on 10 Oct 11) completeness check: complete | info & rep check: concluded |
Monitoring period | 28 Jul 10 - 27 Apr 11 |
Monitoring report | Monitoring report (112 KB) |
Request for issuance | Signed form (103 KB) |
Amount of CERs |
CERs issued up to 31 December 2012:
91,615
Serial Range:
Block start: CN-5-435348570-1-1-0-2017
Block end: CN-5-435440184-1-1-0-2017
|
Verification and certification reports |
Certification report (88 KB)
Verification report (244 KB) |
Additional documents |
ER calculation sheet (36 KB)
Monitoring report Ver. 03 (114 KB) |
Offset now: visit the United Nations Carbon Offset Platform