Project:
0812 BOG and COG Utilisation for Combined Cycle Power CDM Project in Jinan Iron & Steel Works
- Issuance Request
Project | 0812: BOG and COG Utilisation for Combined Cycle Power CDM Project in Jinan Iron & Steel Works |
---|---|
ISSUANCE STATUS | Issued (on 08 Feb 12) completeness check: complete | info & rep check: concluded |
Monitoring period | 16 Nov 10 - 16 May 11 |
Monitoring report |
![]() |
Request for issuance |
![]() |
Amount of CERs |
CERs issued up to 31 December 2012:
820,320
Serial Range:
Block start: CN-5-508030706-1-1-0-812
Block end: CN-5-508851025-1-1-0-812
|
Verification and certification reports |
![]() ![]() |