12:20 12 Mar 25
Project:
6447 Zhejiang Tangcun 32MW Hydropower Project
- Issuance Request
Project | 6447: Zhejiang Tangcun 32MW Hydropower Project |
---|---|
ISSUANCE STATUS | Issued (on 10 May 24) completeness check: complete | info & rep check: concluded |
Monitoring period | 01 Jan 16 - 19 Jun 19 |
Monitoring report |
![]() |
Requests for post-registration changes containing applicable deviations | PRC-6447-004 - Approved |
Requests for post-registration changes submitted with the issuance request | PRC-6447-004 |
Request for issuance |
![]() |
Amount of CERs |
CERs issued from 01 Jan 2013 until 31 December 2020:
74,636
Serial Range:
Block start: CN-5-1196637290-2-2-0-6447
Block end: CN-5-1196711925-2-2-0-6447
|
Verification and certification reports |
VVS/VVM version:
VVS-PA 3.0
![]() ![]() |
Additional documents |
![]() ![]() |
Offset now: visit the United Nations Carbon Offset Platform
Connect with us: