Project: 3066 Hunan Qidong Kaidi Biomass Power Project - Issuance Request
Project 3066: Hunan Qidong Kaidi Biomass Power Project
 
ISSUANCE STATUS Issued (on 19 Sep 14)   completeness check: complete | info & rep check: concluded
Monitoring period 01 Oct 11 - 31 Dec 12
Monitoring report Monitoring report (909 KB)
 
Request for issuance Signed form (485 KB)
Amount of CERs CERs issued up to 31 December 2012: 61,397
Verification and certification reports VVS/VVM version: VVS 6.0
Certification report (588 KB)
Verification report (588 KB)
Additional documents MR (708 KB)
ER (99 KB)
Statement about the construction status of Qidong Kaidi project phase II (260 KB)
Project IRR-Phase I-basen on registered version (141 KB)
Project IRR-Phase I-based on validation opinion on change in revised PDD (144 KB)

Previous submissions

Submission date Outcome
28 Mar 14 CC complete | I&R incomplete