Submission incomplete:
Scope: The verification report does not describe the reasons for the phased-implementation delay and does not present the expected implementation dates. (VVS v6, para 263 (a))
Issue: The registered PDD (p.10) indicates that the construction work for Phase II will begin one year after the Phase I begins operation. The monitoring report (p.2) shows that Phase I was put into operation since 05/10/2010. The verification report (p.7) confirms that Phase II has not been put into construction and is still under consideration by the project developer. However, information on the reasons for the implementation delay and expected implementation dates has not been provided.