Project:
1859 China Fujian Putian LNG Generation Project
- Issuance Request
Project | 1859: China Fujian Putian LNG Generation Project |
---|---|
ISSUANCE STATUS | Issued (on 10 Apr 12) completeness check: complete | info & rep check: concluded |
Monitoring period | 14 Jan 09 - 27 Sep 09 |
Monitoring report | Monitoring report (239 KB) |
Note:
Issuance request(s) for this monitoring period have been previously considered: - Status: Withdrawn (Request for review period: 07 Apr 11 - 04 May 11) |
|
Request for issuance | Signed form (37 KB) |
Amount of CERs |
CERs issued up to 31 December 2012:
257,281
Serial Range:
Block start: CN-5-535871721-1-1-0-1859
Block end: CN-5-536129001-1-1-0-1859
|
Verification and certification reports |
Certification report (39 KB)
Verification report (610 KB) |
Additional documents |
Revised Monitoring Report (ref.1859-1) Putian LNG Project (885 KB)
ER Calculation (ref.1859-1) Putian LNG Project (77 KB) |
Previous submissions
Submission date | Outcome |
---|---|
25 Nov 11 | CC complete | I&R incomplete |