03:39 23 Feb 25
Project:
0958 2 x 5 MW Baner khad & Iku khad small hydroelectric project for a grid system
- Issuance Request
Project | 0958: 2 x 5 MW Baner khad & Iku khad small hydroelectric project for a grid system |
---|---|
ISSUANCE STATUS | Issued (on 28 Feb 24) completeness check: complete | info & rep check: concluded |
Monitoring period | 01 Jan 13 - 30 Jun 19 |
Monitoring report |
![]() |
Requests for post-registration changes containing applicable deviations | PRC-0958-001 - Approved |
Request for issuance |
![]() |
Amount of CERs |
CERs issued from 01 Jan 2013 until 31 December 2020:
190,881
Serial Range:
Block start: IN-5-329837836-2-2-0-958
Block end: IN-5-330028716-2-2-0-958
|
Verification and certification reports |
VVS/VVM version:
VVS-PA 3.0
![]() ![]() |
Additional documents |
![]() ![]() |
Offset now: visit the United Nations Carbon Offset Platform