Project: 10365 100-MW Solar PV Power Plant at Quaid-e-Azam Solar Park, Lal Sohanra, Cholistan, Bahawalpur, Pakistan - Issuance Request
Project 10365: 100-MW Solar PV Power Plant at Quaid-e-Azam Solar Park, Lal Sohanra, Cholistan, Bahawalpur, Pakistan
 
ISSUANCE STATUS Issued (on 13 Jan 21)   completeness check | info & rep check: concluded
Monitoring period 22 Feb 18 - 21 Feb 19
Monitoring report Monitoring report (848 KB)
 
Request for issuance Signed form (340 KB)
Amount of CERs CERs issued from 01 Jan 2013 until 31 December 2020: 95,237
Serial Range: Block start: PK-5-9810559-2-2-0-10365     Block end: PK-5-9905795-2-2-0-10365
Verification and certification reports VVS/VVM version: VVS-PA 2.0
Certification report (497 KB)
Verification report (497 KB)
Additional documents Monitoring_Report_for_PA10365-11.12 (756 KB)
Emission_reductions_spreadsheet (22 KB)

Previous submissions

Submission date Outcome
12 Jun 20 CC complete | I&R incomplete