00:37 18 May 25
Project:
3054 Henan Xinxiang 24MW Biomass based Cogeneration Project
- Issuance Request
Project | 3054: Henan Xinxiang 24MW Biomass based Cogeneration Project |
---|---|
ISSUANCE STATUS | Issued (on 24 May 13) completeness check: complete | info & rep check: concluded |
Monitoring period | 11 Jul 11 - 31 Dec 12 |
Monitoring report |
![]() |
Requests for post-registration changes submitted with the issuance request | PRC-3054-001 |
Request for issuance |
![]() |
Amount of CERs |
CERs issued up to 31 December 2012:
186,473
Serial Range:
Block start: CN-5-821501626-1-1-0-3054
Block end: CN-5-821688098-1-1-0-3054
|
Verification and certification reports |
VVS/VVM version:
VVS 3.0
![]() ![]() |