10066 20 MW BEL Wind Power Project in Maharashtra
- Issuance Request
Project | 10066: 20 MW BEL Wind Power Project in Maharashtra |
---|---|
ISSUANCE STATUS | Issued (on 19 Apr 22) completeness check | info & rep check: concluded |
Monitoring period | 16 Dec 14 - 30 Nov 20 |
Monitoring report |
![]() |
Submission of comments to the DOE | |
Request for issuance |
![]() |
Amount of CERs |
CERs issued from 01 Jan 2013 until 31 December 2020:
131,283
Serial Range:
Block start: IN-5-284328774-2-2-0-10066
Block end: IN-5-284460056-2-2-0-10066
|
Verification and certification reports |
VVS/VVM version:
VVS-PA 3.0
![]() ![]() |
Additional documents |
![]() ![]() |
Previous submissions
Submission date | Outcome |
---|---|
12 Mar 21 | CC complete | I&R incomplete |