Project: 10632 Hasang Hydro Electric Power Plant - Issuance Request
Project 10632: Hasang Hydro Electric Power Plant
 
ISSUANCE STATUS Provisional (awaiting guidance from the CMP at CMP 16)   completeness check: complete | info & rep check: concluded
Monitoring period 01 Nov 21 - 31 Mar 22
Monitoring report Monitoring report (579 KB)
Requests for post-registration changes submitted with the issuance request PRC-10632-002
 
Request for issuance Signed form (105 KB)
Amount of CERs CERs from 01 Jan 2021: 112,651
Verification and certification reports VVS/VVM version: VVS-PA 3.0
Certification report (781 KB)
Verification report (781 KB)
Additional documents MR_Hasang Hydro Electric Power Plant (10632)_4th (589 KB)