7789 Punta Pereira biomass power plant.
- Crediting Period Renewal Request
[]
| Project |
7789: Punta Pereira biomass power plant.
- project design document (2499 KB)
PDD appendices Appendix 1 - Untitled (uploaded 28 Apr 22 16:27:13) (234 KB)
- crediting period renewal form (89 KB)
|
|---|---|
| Methodologies Used |
ACM0006 ver. 15 -
Electricity and heat generation from biomass
|
| VVS Version | VVS-PA 3.0 |
| Standardized baselines used | N/A |
| Amount of Reductions | 55,342 metric tonnes CO2 equivalent per annum |
| Validation Opinion |
Validation opinion (366 KB)
|
| Renewal Date | 23 Jul 22 (Renewable) Provisional (awaiting guidance from the CMP at CMP 16) (view history) completeness check: complete info & rep check: concluded |
| Crediting Period (requested for renewal) |
30 Apr 21 - 29 Apr 28
Other crediting period(s): 30 Apr 14 - 29 Apr 21 |
| Requests for Issuance