Project:
6721 Ryesonggang Hydropower Plant No.4, DPR Korea
- Issuance Request
Project | 6721: Ryesonggang Hydropower Plant No.4, DPR Korea |
---|---|
ISSUANCE STATUS | Issued (on 22 Mar 18) completeness check | info & rep check: concluded |
Monitoring period | 01 Apr 16 - 31 Mar 17 |
Monitoring report |
![]() |
Request for issuance |
![]() |
Amount of CERs |
CERs issued from 01 Jan 2013 until 31 December 2020:
20,050
Serial Range:
Block start: KP-5-372150-2-2-0-6721
Block end: KP-5-392199-2-2-0-6721
|
Verification and certification reports |
VVS/VVM version:
VVS 9.0
![]() ![]() |
Additional documents |
![]() ![]() |
Previous submissions
Submission date | Outcome |
---|---|
06 Oct 17 | CC complete | I&R incomplete |