2199 48 MW Duduluo River Hydroelectric Power Plant
- Issuance Request
Project | 2199: 48 MW Duduluo River Hydroelectric Power Plant |
---|---|
ISSUANCE STATUS | Issued (on 16 Dec 16) completeness check | info & rep check: concluded |
Monitoring period | 01 Jan 13 - 29 Feb 16 |
Monitoring report | Monitoring report (93 KB) |
Request for issuance | Signed form (235 KB) |
Amount of CERs |
CERs issued from 01 Jan 2013 until 31 December 2020:
431,043
Serial Range:
Block start: CN-5-1019965530-2-2-0-2199
Block end: CN-5-1020396572-2-2-0-2199
|
Verification and certification reports |
VVS/VVM version:
VVS 9.0
Certification report (524 KB) Verification report (524 KB) |
Additional documents |
MR_2199 duduluo 5th final clean 20161009 clean.pdf (204 KB)
1 Emission Reduction calculation for duduluo.xls (52 KB) |
Previous submissions
Submission date | Outcome |
---|---|
02 Aug 16 | CC complete | I&R incomplete |