Project: 1620 Hedcor Sibulan 42.5 MW Hydroelectric Power Project - Issuance Request
Project 1620: Hedcor Sibulan 42.5 MW Hydroelectric Power Project
 
ISSUANCE STATUS Issued (on 10 Aug 17)   completeness check: complete | info & rep check: concluded
Monitoring period 26 Dec 13 - 25 Aug 16
Monitoring report Monitoring report (2382 KB)
Requests for post-registration changes submitted with the issuance request PRC-1620-003
 
Request for issuance Signed form (392 KB)
Amount of CERs CERs issued from 01 Jan 2013 until 31 December 2020: 392,561
Serial Range: Block start: PH-5-2498179-2-2-0-1620     Block end: PH-5-2890739-2-2-0-1620
Verification and certification reports VVS/VVM version: VVS 9.0
Certification report (847 KB)
Verification report (847 KB)
Additional documents MR (1057 KB)
ER sheet (780 KB)