Project: 1620 Hedcor Sibulan 42.5 MW Hydroelectric Power Project - Request for post-registration changes
Project 1620 Hedcor Sibulan 42.5 MW Hydroelectric Power Project
PRC ref PRC-1620-003
Process track Issuance
DOE CTI Certification
Methodology(ies) and/or Standardized Baseline(s)
applied at the post-registration changes
No changes
Methodology(ies) list
Standardized baseline(s) list
DOE conducted validation of the changes When performing a verification for the project activity or PoA stated above (See footnote 1 below)
Type of submission Permanent changes from the monitoring plan or the monitoring methodology
  • All changes are in Appendix 1 of the CDM project standard? Yes
Applicable crediting period 26 Feb 10 - 25 Feb 17
Assessment opinion Assessment opinion (557 KB)
Revised PDD Revised PDD (1470 KB)   Revised PDD - track changes (1472 KB)
Supplementary documents
Signed form Signed form (1809 KB)
DOE clarification
VVS version VVS 9.0
Current status 10 Aug 17 - Approved
Effective approval date: 10 Aug 17
Historic statuses 12 Jul 17 - Request published