02:20 08 Jul 25
Project:
1411 La Cascada 2.3 MW Hydroelectric Project
- Issuance Request
Project | 1411: La Cascada 2.3 MW Hydroelectric Project |
---|---|
ISSUANCE STATUS | Issued (on 15 Jul 10) |
Monitoring period | 27 Jan 08 - 31 Aug 09 |
Monitoring report |
![]() |
Request for issuance |
![]() Before corrections: ![]() |
Amount of CERs |
CERs issued up to 31 December 2012:
8,492
Serial Range:
Block start: CO-5-754880-1-1-0-1411
Block end: CO-5-763371-1-1-0-1411
Before corrections: 8492 |
Verification and certification reports |
![]() ![]() Before corrections: ![]() ![]() |
Additional documents |
![]() ![]() ![]() Before corrections: ![]() ![]() |
Request for review |
Request 1
Request 2 Request 3 EB meeting: EB54 (at which the Board considers the request(s) for review, decides whether to undertake the review and, if so, determine its scope and selects a review team) Initial comments: ![]() |
Offset now: visit the United Nations Carbon Offset Platform
Connect with us: