0918 Energas Varadero Conversion from Open Cycle to Combined Cycle Project
- Issuance Request
Project | 0918: Energas Varadero Conversion from Open Cycle to Combined Cycle Project |
---|---|
ISSUANCE STATUS | Withdrawn (on 09 Jul 12) completeness check: complete | info & rep check: concluded |
Monitoring period | 01 Jul 08 - 31 Dec 10 |
Monitoring report |
![]() |
Note:
Issuance request(s) for this monitoring period have been re-submitted: - Status: Rejected (Request for review period: 04 Dec 12 - 31 Dec 12) - Status: Issued (Request for review period: 19 Sep 14 - 16 Oct 14) |
|
Request for issuance |
![]() |
Amount of CERs |
CERs issued up to 31 December 2012:
648,295
|
Verification and certification reports |
![]() ![]() |
Additional documents |
![]() ![]() ![]() |
Request for review |
Request 1
Request 2 Request 3 |
Previous submissions
Submission date | Outcome |
---|---|
03 Feb 12 | CC complete | I&R incomplete |