11:50 15 May 25
Project:
0904 Guangrun Hydropower Project in Hubei Province, P.R. China
- Issuance Request
Project | 0904: Guangrun Hydropower Project in Hubei Province, P.R. China |
---|---|
ISSUANCE STATUS | Issued (on 26 Feb 15) completeness check: complete | info & rep check: concluded |
Monitoring period | 01 Jan 11 - 28 Feb 14 |
Monitoring report |
![]() |
Requests for post-registration changes submitted with the issuance request | PRC-0904-001 |
Request for issuance |
![]() |
Amount of CERs |
CERs issued up to 31 December 2012:
20,566
CERs issued from 01 Jan 2013 until 31 December 2020: 22,683 Total amount of CERs: 43,249
Serial Range:
Block start: CN-5-911741236-1-1-0-904
Block end: CN-5-911761801-1-1-0-904
Serial Range: Block start: CN-5-911761802-2-2-0-904 Block end: CN-5-911784484-2-2-0-904 |
Verification and certification reports |
VVS/VVM version:
VVS 7.0
![]() ![]() |
Additional documents |
![]() ![]() |
Offset now: visit the United Nations Carbon Offset Platform