09:49 25 Nov 24
Project:
0773 Ceran's Monte Claro Run of River Hydropower Plant CDM Project Activity
- Issuance Request
Project | 0773: Ceran's Monte Claro Run of River Hydropower Plant CDM Project Activity |
---|---|
ISSUANCE STATUS | Issued (on 23 Jan 13) completeness check: complete | info & rep check: concluded |
Monitoring period | 01 May 11 - 29 Feb 12 |
Monitoring report | Monitoring report (411 KB) |
Request for issuance | Signed form (519 KB) |
Amount of CERs |
CERs issued up to 31 December 2012:
103,210
Serial Range:
Block start: BR-5-79939255-1-1-0-773
Block end: BR-5-80042464-1-1-0-773
|
Verification and certification reports |
VVS/VVM version:
VVS 2.0
Certification report (78 KB) Verification report (949 KB) |
Additional documents |
Ceran_CER_2012.06.05_v.2 (146 KB)
Ceran_MR_2012.06.05_v.2 (422 KB) |
Previous submissions
Submission date | Outcome |
---|---|
23 Jul 12 | CC complete | I&R incomplete |
23 Sep 12 | CC incomplete |