11:39 11 Jan 25
Project:
0386 Seguntor Bioenergy 11.5MW EFB Power Plant
- Issuance Request
Project | 0386: Seguntor Bioenergy 11.5MW EFB Power Plant |
---|---|
ISSUANCE STATUS | Issued (on 11 Jun 13) completeness check: complete | info & rep check: concluded |
Monitoring period | 01 Aug 11 - 31 Jul 12 |
Monitoring report | Monitoring report (347 KB) |
Requests for post-registration changes submitted with the issuance request | PRC-0386-001 |
Request for issuance | Signed form (540 KB) |
Amount of CERs |
CERs issued up to 31 December 2012:
390,592
Serial Range:
Block start: MY-5-5795442-1-1-0-386
Block end: MY-5-6186033-1-1-0-386
|
Verification and certification reports |
VVS/VVM version:
VVS 3.0
Certification report (345 KB) Verification report (345 KB) |
Additional documents |
Monitoring Report (189 KB)
ER spreadsheet (MP4) (556 KB) |
Offset now: visit the United Nations Carbon Offset Platform