Project: 0386 Seguntor Bioenergy 11.5MW EFB Power Plant - Request for post-registration changes
Project 0386 Seguntor Bioenergy 11.5MW EFB Power Plant
PRC ref PRC-0386-001
Process track Issuance
DOE KBS
Methodology(ies) and/or Standardized Baseline(s)
applied at the post-registration changes
Methodology(ies) list
Standardized baseline(s) list
DOE conducted validation of the changes When performing a verification for the project activity or PoA stated above (See footnote 1 below)
Type of submission Corrections that do not affect project design
  • All changes are in Appendix 1 of the CDM project standard? Yes

Changes to the project or programme design
  • Changes have an impact on: None of the above
Applicable crediting period 05 Feb 09 - 04 Feb 16
Assessment opinion Assessment opinion (345 KB)
Revised PDD Revised PDD (1840 KB)   Revised PDD - track changes (1874 KB)
Supplementary documents Appendix 1 - PDDER estimation_Seguntor.xls (557 KB)
Signed form Signed form (1232 KB)
DOE clarification
VVS version VVS 2.0
Current status 11 Jun 13 - Approved
Effective approval date: 11 Jun 13
Historic statuses 13 May 13 - Request published