13:58 02 Feb 26
Project:
0386 Seguntor Bioenergy 11.5MW EFB Power Plant
- Request for post-registration changes
| Project | 0386 Seguntor Bioenergy 11.5MW EFB Power Plant |
|---|---|
| PRC ref | PRC-0386-001 |
| Process track | Issuance |
| DOE | KBS |
|
Methodology(ies) and/or Standardized Baseline(s)
applied at the post-registration changes |
|
| Methodology(ies) list | |
| Standardized baseline(s) list | |
| DOE conducted validation of the changes | When performing a verification for the project activity or PoA stated above (See footnote 1 below) |
| Type of submission |
Corrections that do not affect project design
Changes to the project or programme design
|
| Applicable crediting period | 05 Feb 09 - 04 Feb 16 |
| Assessment opinion |
Assessment opinion (345 KB)
|
| Revised PDD |
Revised PDD (1840 KB)
Revised PDD - track changes (1874 KB)
|
| Supplementary documents |
Appendix 1 - PDDER estimation_Seguntor.xls (557 KB)
|
| Signed form |
Signed form (1232 KB)
|
| DOE clarification | |
| VVS version | VVS 2.0 |
| Current status | 11 Jun 13 -
Approved
Effective approval date: 11 Jun 13
|
| Historic statuses |
13 May 13 -
Request published |

Assessment opinion
Appendix 1 - PDDER estimation_Seguntor.xls