23:30 03 Nov 24
Project:
0259 Trupan Biomass Power Plant in Chile
- Issuance Request
Project | 0259: Trupan Biomass Power Plant in Chile |
---|---|
ISSUANCE STATUS | Issued (on 15 Jul 08) |
Monitoring period | 01 Oct 06 - 30 Sep 07 |
Monitoring report | Monitoring report (224 KB) |
Request for issuance |
Signed form (114 KB)
Before corrections: Signed form (131 KB) |
Amount of CERs |
CERs issued up to 31 December 2012:
119,813
Serial Range:
Block start: CL-5-2735719-1-1-0-259
Block end: CL-5-2855531-1-1-0-259
Before corrections: 120835 |
Verification and certification reports |
Certification report (212 KB)
Verification report (212 KB) Before corrections: Certification report (173 KB) Verification report (173 KB) |
Additional documents |
Revised Monitoring Report Version 2 (179 KB)
Revised CER Spreadsheet (275 KB) Before corrections: CER Spreadsheet (261 KB) Revised Monitoring Report (204 KB) |
Request for review |
Request 1
Request 2 Request 3 Request 4 EB meeting: EB38 (at which the Board considers the request(s) for review, decides whether to undertake the review and, if so, determine its scope and selects a review team) Initial comments: DOE Initial comments (46 KB) Trupan monit 2006-2007 (263 KB) |
Offset now: visit the United Nations Carbon Offset Platform
Connect with us: