04:26 27 Dec 24
Project:
0258 Nueva Aldea Biomass Power Plant Phase 1
- Crediting Period Renewal Request
[]
Project |
0258: Nueva Aldea Biomass Power Plant Phase 1
- project design document (2700 KB) (approved - - 31 Aug 2015 - view previous) - crediting period renewal form (108 KB) |
---|---|
Methodologies Used |
ACM0006 ver. 12 -
Consolidated methodology for electricity and heat generation from biomass
|
VVS Version | |
Standardized baselines used | N/A |
Amount of Reductions | 193,908 metric tonnes CO2 equivalent per annum |
Validation Opinion |
Validation opinion (794 KB)
Validation opinion on post-registration changes (2113 KB) |
Renewal Date | 01 Mar 14 (Renewable) (view history) |
Crediting Period (requested for renewal) |
01 Jan 12 - 31 Dec 18
Other crediting period(s): 01 Jan 05 - 31 Dec 11 01 Jan 19 - 31 Dec 25 |
Requests for Issuance
and related documentation |
Monitoring report: 01 Jan 2012 - 31 Dec 2013 (2026 KB) Issuance request state: Issued CERs requested up to 31 December 2012: 113736 CERs requested from 01 Jan 2013 until 31 December 2020: 103544 Serial Range: Block start: CL-5-22485864-1-1-0-258 Block end: CL-5-22599599-1-1-0-258 Serial Range: Block start: CL-5-22599600-2-2-0-258 Block end: CL-5-22703143-2-2-0-258 [Full view and history] Monitoring report: 01 Jan 2014 - 31 Dec 2015 (1405 KB) Issuance request state: Issued CERs requested from 01 Jan 2013 until 31 December 2020: 252641 Serial Range: Block start: CL-5-29946196-2-2-0-258 Block end: CL-5-30198836-2-2-0-258 [Full view and history] Monitoring report: 01 Jan 2016 - 31 Dec 2018 (1536 KB) Issuance request state: Awaiting issuance request [Full view and history] |
Offset now: visit the United Nations Carbon Offset Platform
Connect with us: