Project: 10194 5MW Thap Sakae Photovoltaic Solar Cell Power Plant Project, Thailand - Issuance Request
Project 10194: 5MW Thap Sakae Photovoltaic Solar Cell Power Plant Project, Thailand
 
ISSUANCE STATUS Issued (on 02 May 18)   completeness check: complete | info & rep check: concluded
Monitoring period 01 Aug 16 - 31 Mar 17
Monitoring report Monitoring report (426 KB)
Requests for post-registration changes submitted with the issuance request PRC-10194-001
 
Request for issuance Signed form (194 KB)
Amount of CERs CERs issued from 01 Jan 2013 until 31 December 2020: 1,788
Serial Range: Block start: TH-5-13190645-2-2-0-10194     Block end: TH-5-13192432-2-2-0-10194
Verification and certification reports VVS/VVM version: VVS-PA 1.0
Certification report (1048 KB)
Verification report (1048 KB)
Additional documents Copy of ER Thap Sakae (29062017) (21 KB)
MR Thapsakae_v06 (463 KB)
PDD EGAT Thap Sakae_v08_9Mar18 (clean).pdf (1156 KB)
PDD EGAT Thap Sakae_v08_9Mar18 (track change)_no Thai.pdf (1142 KB)