Project: 4837 Guangdong Longgaoshan Wind Power Project - Issuance Request
Project 4837: Guangdong Longgaoshan Wind Power Project
 
ISSUANCE STATUS Issued (on 26 Apr 13)   completeness check: complete | info & rep check: concluded
Monitoring period 07 Jun 11 - 29 Feb 12
Monitoring report Monitoring report (200 KB)
Requests for post-registration changes submitted with the issuance request PRC-4837-001
 
Request for issuance Signed form (62 KB)
Amount of CERs CERs issued up to 31 December 2012: 65,791
Serial Range: Block start: CN-5-806863632-1-1-0-4837     Block end: CN-5-806929422-1-1-0-4837
Verification and certification reports VVS/VVM version: VVS 3.0
Certification report (258 KB)
Verification report (1279 KB)
Additional documents ER_Longgaoshan (35 KB)
MR_Longgaoshan (417 KB)

Previous submissions

Submission date Outcome
29 Jun 12 CC complete | I&R incomplete
11 Dec 12 CC incomplete