09:26 18 May 25
Project:
3115 17.6 MW captive grid connected electricity generation from wind energy project by Chennai Petroleum Corporation Limited.
- Issuance Request
Project | 3115: 17.6 MW captive grid connected electricity generation from wind energy project by Chennai Petroleum Corporation Limited. |
---|---|
ISSUANCE STATUS | Issued (on 07 Apr 15) completeness check: complete | info & rep check: concluded |
Monitoring period | 06 May 10 - 15 Jul 12 |
Monitoring report |
![]() |
Status of a monitoring report | The DOE has raised one or more corrective action requests or clarification requests, for which no response has been received from the project participant or the coordinating/managing entity |
Requests for post-registration changes submitted with the issuance request | PRC-3115-001 |
Request for issuance |
![]() |
Amount of CERs |
CERs issued up to 31 December 2012:
67,464
Serial Range:
Block start: IN-5-204416381-1-1-0-3115
Block end: IN-5-204483844-1-1-0-3115
|
Verification and certification reports |
VVS/VVM version:
VVS 7.0
![]() ![]() |
Additional documents |
![]() ![]() |
Offset now: visit the United Nations Carbon Offset Platform