Project:
1280 2.2 MW hydropower plant in Birsinghpur, Madhya Pradesh of Ascent Hydro Projects Limited (AHPL)
- Crediting Period Renewal Request
[]
Project |
1280: 2.2 MW hydropower plant in Birsinghpur, Madhya Pradesh of Ascent Hydro Projects Limited (AHPL)
- ![]() PDD appendices ![]() - ![]() |
---|---|
Methodologies Used |
AMS-I.D. ver. 18 -
Grid connected renewable electricity generation
|
VVS Version | VVS-PA 3.0 |
Standardized baselines used | N/A |
Amount of Reductions | 12,980 metric tonnes CO2 equivalent per annum |
Validation Opinion |
![]() |
Renewal Date | 04 Feb 23 (Renewable) Provisional (awaiting guidance from the CMP at CMP 16) (view history) completeness check: complete info & rep check: concluded |
Crediting Period (requested for renewal) |
25 Nov 21 - 24 Nov 28
Other crediting period(s): 25 Nov 07 - 24 Nov 14 15 Jun 15 - 24 Nov 21 |