12:30 17 Dec 25
Project:
1280 2.2 MW hydropower plant in Birsinghpur, Madhya Pradesh of Ascent Hydro Projects Limited (AHPL)
- Crediting Period Renewal Request
[]
| Project |
1280: 2.2 MW hydropower plant in Birsinghpur, Madhya Pradesh of Ascent Hydro Projects Limited (AHPL)
- project design document (819 KB)
PDD appendices Appendix 1 - Untitled (uploaded 24 Nov 22 16:38:44) (44 KB)
- crediting period renewal form (66 KB)
|
|---|---|
| Methodologies Used |
AMS-I.D. ver. 18 -
Grid connected renewable electricity generation
|
| VVS Version | VVS-PA 3.0 |
| Standardized baselines used | N/A |
| Amount of Reductions | 12,980 metric tonnes CO2 equivalent per annum |
| Validation Opinion |
Validation opinion (299 KB)
|
| Renewal Date | 04 Feb 23 (Renewable) Provisional (awaiting guidance from the CMP at CMP 16) (view history) completeness check: complete info & rep check: concluded |
| Crediting Period (requested for renewal) |
25 Nov 21 - 24 Nov 28
Other crediting period(s): 25 Nov 07 - 24 Nov 14 15 Jun 15 - 24 Nov 21 |
| Requests for Issuance
and related documentation |
|

project design document
Appendix 1 - Untitled (uploaded 24 Nov 22 16:38:44)
Offset now: visit the United Nations Carbon Offset Platform
Connect with us: