Project: 1280 2.2 MW hydropower plant in Birsinghpur, Madhya Pradesh of Ascent Hydro Projects Limited (AHPL) - Issuance Request
Project 1280: 2.2 MW hydropower plant in Birsinghpur, Madhya Pradesh of Ascent Hydro Projects Limited (AHPL)
 
ISSUANCE STATUS Issued (on 03 Dec 12)   completeness check: complete | info & rep check: concluded
Monitoring period 01 Jan 09 - 31 Dec 11
Monitoring report Monitoring report (394 KB)
 
Request for issuance Signed form (119 KB)
Amount of CERs CERs issued up to 31 December 2012: 38,170
Serial Range: Block start: IN-5-155364868-1-1-0-1280     Block end: IN-5-155403037-1-1-0-1280
Verification and certification reports VVS/VVM version: VVM 1.2
Certification report (163 KB)
Verification report (934 KB)
Additional documents 64.49_AHPL_ER Sheet.xls (36 KB)
64.49_AHPL_MR_V03.pdf (387 KB)