Project: 1280 2.2 MW hydropower plant in Birsinghpur, Madhya Pradesh of Ascent Hydro Projects Limited (AHPL) - Issuance Request
Project 1280: 2.2 MW hydropower plant in Birsinghpur, Madhya Pradesh of Ascent Hydro Projects Limited (AHPL)
 
ISSUANCE STATUS Issued (on 27 Dec 11)   completeness check: complete | info & rep check: concluded
Monitoring period 25 Nov 07 - 31 Dec 08
Monitoring report Monitoring report (245 KB)
 
Request for issuance Signed form (127 KB)
Amount of CERs CERs issued up to 31 December 2012: 14,277
Serial Range: Block start: IN-5-124308791-1-1-0-1280     Block end: IN-5-124323067-1-1-0-1280
Verification and certification reports Certification report (60 KB)
Verification report (553 KB)
Additional documents 2.2 MW hydropower plant in Birsinghpur - ER (32 KB)
2.2 MW hydropower plant in Birsinghpur - 1280 - MR (148 KB)