06:34 26 Jun 25
Project:
0830 Rialma Companhia Energética I S/A. - Santa Edwiges I Small Hydro Power Plant - Small Scale CDM Project
- Issuance Request
Project | 0830: Rialma Companhia Energética I S/A. - Santa Edwiges I Small Hydro Power Plant - Small Scale CDM Project |
---|---|
ISSUANCE STATUS |
Rejected
|
Monitoring period | 01 Jan 09 - 31 Dec 09 |
Monitoring report |
![]() |
Note:
Issuance request(s) for this monitoring period have been re-submitted: - Status: Issued (Request for review period: 02 Dec 11 - 29 Dec 11) |
|
Request for issuance |
![]() |
Amount of CERs |
CERs issued up to 31 December 2012:
14,005
|
Verification and certification reports |
![]() ![]() |
Additional documents |
![]() ![]() ![]() |
Request for review |
Request 1
Request 2 Request 3 EB meeting: EB58 (at which the review were/will be considered) |
Review documentation | |
Clarification documents |
![]() |
Offset now: visit the United Nations Carbon Offset Platform