Issuance Request for Review Form


CDM project activity/programme of activities
issuance request review form (CDM-ISSR-FORM)
(Version 03.0)

Project title of the project activity or programme of activities (PoA) for which issuance is requestedRialma Companhia Energética I S/A. - Santa Edwiges I Small Hydro Power Plant - Small Scale CDM Project (0830)
DOE that requested for issuance and date of requestBVI (27 Mar 10)
Please indicate, in accordance with paragraphs 65 of the CDM modalities and procedures, for which reason(s) you request review
Incompetence
Please indicate reasons for the request for review
The DOE shall clarify how it confirmed that:
(1) The monitoring of electricity supplied to the grid from the project activity was conducted in accordance with the monitoring plan considering that the monitoring plan has not specified connection of other hydro plants (Santa Edwiges II and III) to the meters.
(2) There has not been any change in the monitoring system since last verification, considering that the last verification report mentioned that the meters at the substation measured electricity delivered to the grid by the project activity whereas the current verification report mentions that the meters located at the substation measured electricity delivered to the grid by three hydropower plants: Santa Edwiges I, II and III.
Date 05 Aug 10